Community Services Center

Update: 10/31/2024

  • Trees and shrubs have been removed in preparation for construction and will be replanted in the spring.
  • Foundation grading was completed this week, and excavation for footers is nearly done.
  • Soil testing has been conducted, and footers will soon be poured to provide a stable foundation.
  • Expect saw cutting and demolition of existing asphalt and concrete in the coming days.
  • Crews are using water to minimize soil drifting.
  • Utility trenching work is scheduled for early November, which may require temporary road closures for safety. We’ll send out notifications as we approach this phase.
  • For everyone’s safety, please stay clear of the construction zone.
  • To receive detailed updates on Community Services Center construction, please subscribe by emailing [email protected]. These newsletters will automatically be sent to adjacent neighbors subscribed to the main email list. If you later wish to unsubscribe from construction-specific updates but continue receiving the regular newsletter, please email us directly instead of using the unsubscribe button. The unsubscribe button will remove you from both newsletters.
construction crew progress
construction crew progress
construction crew progress

Inspiration Community Services Center Project Overview

The new community building is designed to serve as a hub for community gatherings, district events and meetings, recreation, social programming, and equipment storage for both recreation and maintenance purposes.

Construction will begin in October 2024, anticipated completion is May/June 2025. 

Please obey signs and stay out of the construction zone and fenced areas.

Why This Project?
• Inspiration, with 1,916 homes, currently has no indoor communal space.
• The original master plan called for this type of community facility.
• This project is the culmination of a community-led effort that has spanned more than six years.
• The project is on track to stay within the planned $2.1 million budget.

Year-Round Activities & Programming
The community center will provide space for:
• Recreation and fitness programs
• Social events and resident gatherings
• District events and meetings
• Storage for recreational and maintenance equipment

Project Background
• The site was designated for a community facility in successive versions of the master plan.
• It was a primary objective of the 2021 bond refinancing and will complement the existing amenities and recreational spaces.
• The center’s multi-use design maximizes flexibility while serving the diverse needs of the Inspiration community.
• By consolidating activities into one building, the project conserves resources.

Building Location
Floor Plan
Mockup of front view elevation
Mockup of side view elevation