Inspiration Club

building3 building overhead view distance photo overhead building

Email [email protected] to get building update emails 

04/29/2025 – IMD: Construction Update

The Inspiration Club is nearing the finish line, here are this week’s construction highlights:

  • AV system was installed over the weekend and will be finalized in the second week of May.

  • Access control system and security cameras are installed and nearly complete.

  • Electrical work is finished, and the building is now fully lit.

  • The HVAC system is scheduled to be commissioned this Friday.

  • Final inspection is set to take place next week.

Important Reminder: The Inspiration Club is not open and is still an active construction site. For your safety, please stay clear of the construction zone.

We’re getting very close to welcoming you in for the Grand Opening on May 31st, stay tuned for future updates!

04/16/2025 – IMD: Construction Update

Construction at the Inspiration Club continues to progress steadily, with several key milestones reached. Here’s the latest updates: 
  • Hallway and bathroom tile is in and looking great
  • Fixtures are installed
  • Ceiling grid is nearly complete
  • Drywall finishing is done and almost everything is primed
  • Electrical work is nearing completion, with the transformer scheduled to arrive next week
  • HVAC is close to the finish line
  • Carpet installation is also scheduled for next week
We’re getting closer every day to welcoming you into this exciting new space.

04/08/2025 – IMD: Construction Update

Work is progressing steadily! Here’s what’s been completed and what’s coming up:

  • Ductwork and light fixture installation is underway
  • Drywall and gutters are finished
  • Doors have been installed
  • Bathroom tile is complete; tile work in the lobby and hallway is now in progress
  • Carpet installation will happen soon, as interior paint continues.

Electrical Power Notice: As we approach power installation to the building on April 25, please note that street lights (not homes) may temporarily lose power during the day. This should be resolved before nightfall. Thank you for your continued patience and support as we near the finish line!

04/01/2025 – IMD: Construction Update

Construction on our new building is progressing steadily, and we are pleased to share the latest updates:

  • Drywall installation is complete.
  • Garage doors have been installed and interior / exterior doors are being installed this week.
  • Floor tiles and carpet are being installed soon, along with ceiling tiles.
  • Irrigation lines are being updated around the building perimeter.

As we move closer to completion, we appreciate your patience and support. Please remember that this remains a closed construction site. For safety reasons, only authorized personnel are permitted on-site.

03/26/2025 – IMD: Construction Update

We’re excited to share the latest progress on the Inspiration Club building! Construction is moving along nicely, and we’re getting closer to completion.

Completed:

  • Interior drywall installed
  • Asphalt replaced on Zante 
  • Storm water line connected to Aurora’s stormwater system

In Progress:

  • HVAC installation
  • Electrical installation
  • Exterior speakers and lighting installation

Coming Up Next:

  • Interior painting
  • Security and access control systems installation

We’ll continue to share updates as the project progresses. Thank you for your support and patience — we’re looking forward to opening the Inspiration Club for everyone to enjoy soon!

Stay tuned for more updates!

03/13/2025 – IMD: Construction Update

We’d like to provide you with an update on the ongoing building construction and an important street closure notice:

  • HVAC & electrical rough-ins are ongoing.

  • Stucco and exterior stonework are fully complete.

  • Drywall is 65% complete, with interior painting scheduled to begin next week.

  • Electrical installation in soffits is in progress.

  • Grading work is underway around the building exterior.

  • Roof is almost complete.

  • Upcoming work includes restroom ceilings and door frame installation.

Street Closure Notice
To permanently patch the asphalt on E. Glidden Drive—replacing the temporary patch installed after the initial excavation—there will be a street closure in front of two affected houses. Work is scheduled to begin on Thursday, March 13th, and is expected to continue through Friday.

Please see the map below for details on the affected area.

We appreciate your patience and cooperation as we work toward completing this project. Should you have any questions or concerns, please don’t hesitate to reach out.

03/07/2025 – IMD: Construction Update

Drywall has been installed and being finished, along with stucco and stonework on the exterior. The project is on time for substantial completion in early May, with occupancy coming after that. Next week, a final street closure will be performed to restore the asphalt on Glidden Drive, in the same location as the prior closure. This asphalt work is pending scheduling and weather, tentatively mid next week. Notifications will be send via this newsletter, with the two adjacent homes receiving additional notification. View the building construction webpage for more details.

02/12/2025 – IMD: Construction Update

Here are the latest building construction updates:

  • Water Supply: Aurora Water has successfully charged the fire hydrant at the Clubhouse location.  The pressure tests were done and successfully passed.
  • Electrical Work: The electrical rough-in is currently underway, bringing us closer to finalizing the essential infrastructure.
  • HVAC Progress: The HVAC system installation is almost complete. 
  • Inspections: Storm water and safety inspections have been completed, ensuring compliance with all necessary regulations.

Looking ahead: In the next three weeks look for the following work to be done:

  • Interior and exterior door framing
  • Drywall hanging
  • Continued work on exterior stucco, stone, and rigid insulation

Thank you for your continued support and patience as we move closer to the next phase. If you have any questions or concerns, feel free to contact [email protected].

02/07/2025 – IMD: Construction Update

Here is the latest progress:

  • Electrical Walk Completed – The team recently conducted a thorough electrical walk throughout the community. This step ensures that all outlets, switches, and lights are placed exactly where they need to be for your convenience and comfort.
  • Full Insulation – We’re happy to announce that the building is now fully insulated!
  • HVAC & Plumbing Progress – Most of the HVAC and plumbing systems are now completed and ready for the next stages. This brings us one step closer to ensuring optimal temperature control and functionality throughout the community.
  • Exterior Stucco Installation – The exterior of the buildings is starting to take shape with the stucco installation underway. It’s exciting to see the structure transform into the beautiful, finished community we’ve all been looking forward to!

01/29/2025 – IMD: Construction Update

Things are moving full steam ahead, and we can’t wait for you to see the results. Here’s what’s been happening:

  • Audio/Visual Design Discussions: We’ve been hard at work planning the audio/visual features for the building. From cutting-edge sound systems to state-of-the-art visual setups, we’re designing a space that’s as functional as it is impressive!
  • Doors and Hardware Ordered: The doors and hardware have officially been ordered and are expected to arrive by February 15th
  • Spray Foam Insulation Complete: All of the spray foam insulation is now in place, ensuring the building will be energy-efficient and comfortable for everyone who uses it.
  • HVAC, Plumbing, and Power Updates: This week and next, our team is busy with HVAC and plumbing rough-ins. Power rough-ins are next. We’re getting closer to flipping the switch.
  • Hydrant Testing Done: Hydrant testing has been completed, and we’re just waiting on final approval from Aurora. Once that’s in, we’ll be one step closer to completion.

We’re so grateful for your support as we work to create a space that will benefit our entire community. Stay tuned for more updates. 


01/23/2025 – IMD: Construction Update – Temporary Sidewalk Closure Tomorrow Morning

We want to inform you of an upcoming temporary sidewalk closure that will occur tomorrow morning, Friday, January 24, 2025, for approximately 3-4 hours.

Reason for Closure: Aurora Water requires the installation of a port on a fire hydrant line to facilitate air bleeding during chlorine flushing.

We want to inform you of an upcoming temporary sidewalk closure that will occur tomorrow morning, Friday, January 24, 2025, for approximately 3-4 hours.

  • Reason for Closure: Aurora Water requires the installation of a port on a fire hydrant line to facilitate air bleeding during chlorine flushing.
  • Location: The area between the sidewalk and the curb in the landscaping section along Zante.
  • Timing: The closure will begin early in the morning and last about 3-4 hours.

After this initial work, the affected area will be safely covered and fenced for the weekend while the line undergoes a 48-hour chlorination process. Importantly, the sidewalk will be reopened following the initial work.

We apologize for the short notice and any inconvenience this may cause. If you have any questions or concerns, please feel free to reach out.

The area between the sidewalk and the curb in the landscaping section along Zante.
Timing: The closure will begin early in the morning and last about 3-4 hours.
After this initial work, the affected area will be safely covered and fenced for the weekend while the line undergoes a 48-hour chlorination process. Importantly, the sidewalk will be reopened following the initial work.

We apologize for the short notice and any inconvenience this may cause. If you have any questions or concerns, please feel free to reach out.

01/15/2025 – IMD: Construction Update – Community Services Center Building

Exciting developments are happening this week at the Inspiration Club construction site! Here’s the latest:

  • Roof and Sheathing: Installation is underway this week, bringing us closer to a fully enclosed structure.
  • Spray Foam and Insulation: Scheduled to begin this Friday, ensuring energy efficiency and comfort.
  • Interior Work: More framing and blocking are being completed to shape the interior spaces.
  • HVAC Progress: Overhead installations and rough-ins are set to begin next week.
  • Hydrant Inspections: Aurora Fire will be performing hydrant inspections starting on January 27th.
  • Stucco and Shingles: Stucco application will commence soon, followed by the installation of shingles to finish the roof.

Thank you for your continued support as we move closer to the grand opening of the Inspiration Club. Stay tuned for more updates!

01/07/2025 – IMD: Building Construction Update, Keep your Vehicles Safe

We’re excited to share the latest progress on the community building project. Over the next few days, crews will be focused on completing framing and roofing work. Roofing installation is slated to begin on Friday and continue through the following week. Once the roof is in place, we’ll move on to spray foam insulation, followed by HVAC rough-in work the week after.

Please be aware that due to the nature of the construction and the weather, there may be some Saturday work days for our crews to ensure we stay on schedule. Thank you for your patience and understanding as we continue to make strides toward completing the building!

Community Building

12/31/2024 – IMD: Construction Update – Community Services Center Building

Utilities and sanitary sewer connections have been completed, and the walls are now up. Roofing work is next on the schedule. The storm drainage line around the building is expected to be completed within the next three days. Additionally, the section of sidewalk along Glidden Drive has been repoured, cured, and is now open for use.

The next Inspiration Club Subcommittee meeting is scheduled for Thursday, January 9, at 5:30 p.m. and is open to all residents.

Update: 12/23/2024 – IMD: Construction Update – Community Services Center Building

Construction of the new Community Building continues to make progress. On December 20th, crews poured the sidewalks and curb gutters to provide safe and accessible pathways and channel the rainwater away from the building. Work is also ongoing on the building’s walls, and roof trusses are scheduled for delivery early next week.

Construction Update Construction Update

Walls on Community Building Walls on Community Building

Update: 12/18/2024 IMD: Construction Update – Community Services Center Building

The base slab was poured last week, and wall framing is now underway with the roof trusses being delivered next week. Weather permitting, fresh concrete will be poured on Friday to repair sections of the sidewalk that had been cut as part of the water and sewer connection process. This portion of sidewalk will be inaccessible to foot traffic for a week while the concrete cures, please see the map below. Site cleanup and landscaping grading will follow shortly. Coordination with the City of Aurora for a hydrant flush is also underway. View the building construction webpage for more details.

Sidewalk Map

Update: 12/13/2024 IMD: Construction Update – Community Services Center Building

This week, the water and sewer lines were successfully connected, and the S Zante road closure is expected to end today. We appreciate the community’s patience during this disruption and thank you for your understanding.

The foundation concrete slab has been poured and cured, allowing work to begin on the building’s walls. Finishing the foundation required after-hours work on Wednesday night, we apologize for any inconvenience and are committed to ensuring this is a one-time occurrence.

Update: 12/06/2024 IMD: Construction Update – Community Services Center Building

Starting Monday morning (12/9/2024), there will be a temporary road closure with traffic control in place, on S Zante, between 8808 and 8798, to allow for necessary work connecting the water and sewer mains for the Inspiration Club construction.

The closure will begin on Monday, December 9th and is expected to be completed by Friday, December 13th. Please see the confirmed road closure map for additional details

Road Closure Map

Update: 12/04/2024 IMD: Holly Jolly this Saturday, Zante Street Road Closure

Due to the construction of the Community Services Center, a small portion of Zante Street is anticipated to close for a few days as early as next week. The dates of the road closure have not yet been scheduled, but we will send an update once they are confirmed. Meanwhile, building slabs are already being installed as part of the ongoing construction.

Update: 11/26/2024 IMD: Construction Update – Community Services Center Building

Foundation footings and walls have been poured, and backfill of the foundation is currently underway. The plumber is scheduled to start next week, followed by very minimal underground electrical work. The slab (floor) preparation and pour will take place once the plumbing and electrical work are complete.

Our team met with Aurora last Friday to finalize details about the road closure and paving, which is scheduled for the week of December 9th. Management will notify the two closest homes with a phone call and email, and other neighbors will be notified by email.

A new temporary address sign will soon be installed near the building, indicating the address as 23396 E Glidden Drive.

Road Closure Map

photo of site foundation being backfilled 1 of 2 photo of site foundation being backfilled 2 of 2

Update: 11/19/2024 IMD: Construction Update – Community Services Center Building

  • A small portion of Zante Street is anticipated to close for a few days in early December. This temporary closure will allow for all necessary connections and inspections to be completed at once, avoiding the need for an open trench for over six days.
  • The dates of the road closure have not yet been scheduled. We will send an update once the dates are confirmed. Please plan for alternate routes during this time and refer to the map below for details. Feel free to contact us with questions specific to your property.
  • Concrete footers were poured last Thursday, November 14th.
  • The foundation pour is planned for Wednesday, November 20th.

Update: 11/07/2024 Construction Update – Community Services Center Building

  • Concrete footers are scheduled to be poured this week, as weather allows. The next step is pouring the pad before walls start going up.
  • Our team met with Aurora Water to finalize plans for connecting to the water and sewer systems. We’ll provide more details about any necessary partial road closures, including a map, once dates are confirmed.
  • In the coming weeks, residents can expect to see additional concrete work on the walls and utility trenching around the site.

Update: 11/01/2024 Community Services Center Construction Update, Committee Member Applications

  • Trees and shrubs have been removed in preparation for construction and will be replanted in the spring.
  • Foundation grading was completed this week, and excavation for footers is nearly done.
  • Soil testing has been conducted, and footers will soon be poured to provide a stable foundation.
  • Expect saw cutting and demolition of existing asphalt and concrete in the coming days.
  • Crews are using water to minimize soil drifting.
  • Utility trenching work is scheduled for early November, which may require temporary road closures for safety. We’ll send out notifications as we approach this phase.
  • For everyone’s safety, please stay clear of the construction zone.
  • To receive detailed updates on Community Services Center construction, please subscribe by emailing [email protected]. These newsletters will automatically be sent to adjacent neighbors subscribed to the main email list. If you later wish to unsubscribe from construction-specific updates but continue receiving the regular newsletter, please email us directly instead of using the unsubscribe button. The unsubscribe button will remove you from both newsletters.
construction crew progress
construction crew progress
construction crew progress

Inspiration Community Services Center Project Overview

The new community building is designed to serve as a hub for community gatherings, district events and meetings, recreation, social programming, and equipment storage for both recreation and maintenance purposes.

Construction will begin in October 2024, anticipated completion is May/June 2025. 

Please obey signs and stay out of the construction zone and fenced areas.

Why This Project?
• Inspiration, with 1,916 homes, currently has no indoor communal space.
• The original master plan called for this type of community facility.
• This project is the culmination of a community-led effort that has spanned more than six years.
• The project is on track to stay within the planned $2.1 million budget.

Year-Round Activities & Programming
The community center will provide space for:
• Recreation and fitness programs
• Social events and resident gatherings
• District events and meetings
• Storage for recreational and maintenance equipment

Project Background
• The site was designated for a community facility in successive versions of the master plan.
• It was a primary objective of the 2021 bond refinancing and will complement the existing amenities and recreational spaces.
• The center’s multi-use design maximizes flexibility while serving the diverse needs of the Inspiration community.
• By consolidating activities into one building, the project conserves resources.

Building Location
Floor Plan
Mockup of front view elevation
Mockup of side view elevation